Development update - 22nd March

22 March 2021

The steel frame to the building is now complete in all areas, metal decking has been completed to all floors above the cricket school, with concreting starting on the 15th March.  
Works are on schedule to allow the structure for main student accommodation to commence early April.  Scaffold works are progressing well to the exterior of the building.  And finally, everyone will be pleased to learn that repair to the outfield have now been completed and coming on nicely.

 

As always if you have any queries or wish to discuss this or any of our other projects or developments, please don't hesitate to contact me.

 

Kind regards

Andy Owen 

 