Club development update 18th Nov
18 November 2020
It is fair to say that Rydon have the bit between their teeth and are making up for lost time. It has been almost four weeks since my last update and a lot has happened with the development project in our car park at North Parade.
Drainage across the cricket field will be completed by today (20.11.20) and in the most part the trench which was dug on the outfield has been back filled and covered by our ground staff in preparation for is recovery and restoration ready for next season.
Piling to the new indoor cricket school will also be completed by the close of play 20.11.20 as will 50% of the foundations for the indoor school. Excavations for the North East corner of the student accommodation are ongoing and hoarding to the front elevation has recommenced.
Have a great weekend and stay safe.
Andy Owen